Energy · Wind
Hamburg → Mersin → Erbil (Iraq)
Cargo
3× turbine blades, each 92m × 4.5m × 4m, 30t
Mode
Heavy-lift vessel + SPMT 12-axle line
Transit
32 days door-to-door
Challenge
4 bridges clearance, Baghdad transit, Erbil mountain route
✓ Outcome
Zero damage, 2 days ahead of schedule. Customer signed a 2-year framework.
Energy · Grid
Tubarão (Brazil) → Mersin → Adana
Cargo
320t power transformer, 7m × 5m × 5m, OOG
Mode
Capesize bulk carrier + SPMT 24-axle line
Challenge
Atlantic storm window, Mersin port equipment compatibility
✓ Outcome
Damage-free delivery, sub-station hit Q2 commissioning.
Healthcare · Pharma
Brussels → Tashkent (Uzbekistan)
Cargo
18 t temperature-sensitive vaccines (+2/+8°C)
Mode
B777F belly cargo + Envirotainer RAP/RKN + GDP Frigo TIR
Transit
38 hours door-to-door
Challenge
Tashkent customs documentation, unbroken cold chain
✓ Outcome
Zero temperature breach, vaccine campaign launched 1 week ahead.
Petrochemical
Ulsan (S. Korea) → Aliağa (Turkey)
Cargo
Refinery column 52m × 6m × 6m, 180t pre-fab
Mode
BBK ocean + SPMT 18-axle + temporary bridge reinforcement
Challenge
Aliağa terminal limits, 2 bridge reinforcements, river crossing
✓ Outcome
Hit refinery commissioning date. Customer renewed 5-year SOW.